Thank you for visiting this page. Here you will find information about construction projects happening in your community.

From time to time construction activities may cause interruptions in accessing your driveway, road closures / lane restrictions, and other service impacts. The RMWB is committed to minimizing the impact to residents while we undertake these necessary projects. We ask for your support and cooperation as we make improvements in your neighbourhood.

Please subscribe above to have updates emailed directly to your inbox and check this page regularly for detailed information about construction projects, timelines, and progress.

As always, if you have specific questions or concerns, contact the RMWB Pulse line; 780-743-7000, 1-800-973-9663 or https://pulse.rmwb.ca.

Currently the RMWB is working on:

  1. Water and Sewer Service Projects
    • Water Main/Service Inspection and Testing
    • Stony Mountain Road
    • Willow Lake Road
    • Oak Court
    • Gillmore Drive
    • Singer Drive
    • Cheecham Drive
    • Gregoire Lake to Anzac Force Main
    • Park Drive

Thank you for your cooperation and patience as we work to improve our region.

Thank you for visiting this page. Here you will find information about construction projects happening in your community.

From time to time construction activities may cause interruptions in accessing your driveway, road closures / lane restrictions, and other service impacts. The RMWB is committed to minimizing the impact to residents while we undertake these necessary projects. We ask for your support and cooperation as we make improvements in your neighbourhood.

Please subscribe above to have updates emailed directly to your inbox and check this page regularly for detailed information about construction projects, timelines, and progress.

As always, if you have specific questions or concerns, contact the RMWB Pulse line; 780-743-7000, 1-800-973-9663 or https://pulse.rmwb.ca.

Currently the RMWB is working on:

  1. Water and Sewer Service Projects
    • Water Main/Service Inspection and Testing
    • Stony Mountain Road
    • Willow Lake Road
    • Oak Court
    • Gillmore Drive
    • Singer Drive
    • Cheecham Drive
    • Gregoire Lake to Anzac Force Main
    • Park Drive

Thank you for your cooperation and patience as we work to improve our region.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Water Main/Service Inspection and Testing

5 months

Pidherney’s Civil Construction Company will be testing and inspecting the water improvement work done in your area. In keeping with Alberta Public Health Officials’ guidelines on physical distancing no physical contact will be made, instead residents/businesses will receive a call from Pidherney’s to schedule a date and time between the week of April 14-17, 2020 to conduct the inspection and testing. 

Likewise, we ask that residents/business be available on the scheduled date and time to receive a phone call from Pidherney’s to confirm water usage in the building. No repairs and/or additional work within your building are expected at this time. Should you require assistance, please call: Jason Conlin, Pidherney’s 403-322-0340. 

SERVICE IMPACT

During the testing, you may notice a very short disruption of your water service which will be restored as quickly as possible.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Stony Mountain Road

5 months

Pidherney’s Civil Construction will be returning to your community to continue work on the Rural Water and Sewer Project in the Stony Mountain Road area as well as Road Upgrades. Crews are expected to start mobilizing in the coming days. 

This year Pidherney’s will be completing the water and sewer main service connections and it is anticipated that this work will be completed June 30, 2020. 

SERVICE IMPACT

We do not anticipate any service impact at this time. Notices will be provided in advance should there be any interruptions in services. 

ROAD CLOSURE/DETOUR INFORMATION

To complete the work in a safe manner, there will be lane and road restrictions such as detours in the construction work zones. Access for emergency vehicles will be maintained at all times. 

WORK HOURS

Work to take place from 7:00am – 7:00pm, Monday – Friday with after hours and weekend work as required.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Willow Lake Road, Oak Court & Gillmore Drive

5 months

Pidherney’s Civil Construction will be returning to your community to continue work on the Rural Water and Sewer Project on Willow Lake Road, Oak Court and Gillmore Drive as well as Road Upgrades.
Crews are expected to start mobilizing in the coming days. This year Pidherney’s will be completing the water and sewer main service connections and it is anticipated that this work will be completed June 30, 2020.

SERVICE IMPACT

We do not anticipate any service impact at this time. Notices will be provided in advance should there be any interruptions in services.

ROAD CLOSURE/DETOUR INFORMATION 

To complete the work in a safe manner, there will be lane and road restrictions such as detours in the construction work zones. Access for emergency vehicles will be maintained at all times. 

WORK HOURS

 Work to take place from 7:00am – 7:00pm, Monday – Friday with after hours and weekend work as required.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Singer Drive

4 months

Singer Drive from Highway 881 to Woodward Drive will be closed to through traffic commencing Monday, June 22, 2020 until July 15, 2020. The road is closed to facilitate the water and sewer work and road reconstruction as part of the Rural Water and Sewer Service Project.

WORK HOURS

Work to take place from 7:00am – 7:00pm, Monday – Friday with after hours and weekend work as required.

TRAFFIC MANAGEMENT

Traffic will be managed in the construction area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets. Motorist and pedestrians are asked to obey all traffic signs and posted signs in the construction area as well as not cross/move construction barriers. Access to emergency vehicles will be maintained at all times.

GARBAGE PICK-UP

Residents should continue to put their garbage out as per regular curbside schedule. If required, the contractor will remove bins to an appropriate location for pick up by the municipality. Please ensure that you label your bins with your address.

We apologize for any inconveniences and thank you for your patience as we work to improve our region.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Cheecham Drive

4 months

Cheecham Drive from Park Drive to Cheecham Court will be closed to through traffic commencing Monday, June 29th until Tuesday, June 30th. The road is being closed to complete asphalt removal as part of the Rural Water and Sewer Service Project.

TRAFFIC MANAGEMENT

Traffic will be managed in the construction area for the safety of workers, road users and residents. Local residents access to and from their properties will still be possible using the detour onto Park Drive, Townsend Drive and Hopegood Drive. Road users should expect delays and increased traffic on nearby main and side streets. Motorist and pedestrians are asked to obey all traffic signs and posted signs in the construction area as well as not cross/move construction barriers. Access to emergency vehicles will be maintained at all times.

GARBAGE PICK-UP

Residents should continue to put their garbage out as per regular curbside schedule. If required, the contractor will move bins to an appropriate location for pick up by the municipality. Please ensure that you label your bins with your address.

WORK HOURS

Work to take place from 7:00am – 7:00pm, Monday – Saturday with after hours and weekend work as required.

We apologize for any inconveniences and thank you for your patience as we work to improve our region.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Gregoire Lake to Anzac Force Main

4 months

Every year the Municipality undertakes dozens of construction projects that are aimed at improving and adding to infrastructure in the region.

While our response as a Municipality to COVID-19 is ongoing, we are also focused on continuing the necessary projects this construction season that will improve residents’ quality of life and keep our region running. The construction sector undertakes many significant and important projects in communities across Alberta, which is why the Provincial government deemed it an essential service.

The Municipality’s Contractor, Pipe Quest Projects Ltd will be in your neighborhood for the construction of the Gregoire Lake Estate to Anzac Force Main project. Crews are expected to start mobilizing as early as July 15, 2020 and it is anticipated that the work will be completed end of February 2022. There will be mobilization of heavy equipment getting on and off Highway 881. The force main is required to pump the sewage from Gregoire Lake Estate to the Anzac Wastewater Treatment facility after it is completed.

The project work includes installation of approximately 13KM of HDPE pipeline and the construction of seven access roads off Highway 881 as shown in the map below. The force main alignment is approximately 100 to 500 m south west of Hwy 881 and it runs from Gregoire Lake Estates to Anzac.

Access will be maintained to homes along the force main alignment, and residents will be notified of any interruptions ahead of time. Residence along the ROW may experience increased noise and traffic volume from construction.

NOISE AND VIBRATION MONITORING

There will be noise and some vibration associated with the work. Pipe Quest Projects Ltd is committed to following all municipal bylaws and regulations and will make every effort to minimize noise and vibrations during construction. We ask for your understanding and patience as work progresses.



Share on Facebook Share on Twitter Share on Linkedin Email this link

Park Drive

4 months

Notice of Road Detour and Lane Closure

July 20, 2020 - August 14, 2020


Park Drive from Christina Drive to Cheecham Drive will be closed to through traffic commencing Monday, July 20, 2020 until August 14, 2020. The road is closed to facilitate the water and sewer work and road reconstruction as part of the Rural Water and Sewer Service Project.

TRAFFIC MANAGEMENT

Traffic will be managed in the construction area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets. Motorist and pedestrians are asked to obey all traffic signs and posted signs in the construction area as well as not cross/move construction barriers. Access to emergency vehicles will be maintained at all times. Please obey the one-way signs for the temporary road on Park Drive from Cheecham Drive to Christina Drive.

GARBAGE PICK-UP

Residents should continue to put their garbage out as per regular curbside schedule. If required, the contractor will remove bins to an appropriate location for pick up by the municipality. Please ensure that you label your bins with your address.

We apologize for any inconveniencies and thank you for your patience as we work to improve our region.

WORK HOURS

Work to take place from 7:00am – 7:00pm, Monday – Saturday and from 9:00am –7:00pm on Sundays, with after hours, as required.